Chapman Taylor's 447-bed Waterside student scheme completes in Bristol's Temple Quarter
The practice said the purpose-built student accommodation at 58-62 Avon Street, built by GMI Construction Group on a former industrial site, opened in time for the 2026/27 academic year opposite the University of Bristol's new campus.

Chapman Taylor announced on 20 November 2026 that Waterside, the purpose-built student accommodation (PBSA) scheme it designed at 58-62 Avon Street in Bristol's Temple Quarter, has completed with 447 student bedrooms.
The practice said the project, formerly known as Avon Street, was developed by Tiger Developments with funding from Corebridge Financial, built by GMI Construction Group and is operated by Host. It opened in time to welcome students for the 2026/27 academic year.
Operator Host's property page confirms the building is open for the 2026/27 year and offers en-suite rooms in five, six or eight-bedroom shared flats, as well as private en-suite studios.
GMI Construction Group has described the job as a £50m contract on the site of the former Chanson Foods facility. Adam Taylor, GMI Construction's Regional Director in the Midlands, said at topping out: "It is a privilege to be delivering such a high-profile development in the heart of Bristol."
The design
According to Chapman Taylor, Waterside comprises two residential buildings of eight to 12 storeys, together with a standalone two-storey amenity hub overlooking the harbourside. The buildings are arranged around a central courtyard, and the practice said the design draws on the industrial character of Temple Quarter and its historic railway infrastructure.
Communal facilities include a gym, private dining room, lounge, games room, quiet study spaces, karaoke rooms and a content creation room, Chapman Taylor said. The development is designed to meet BREEAM Excellent.
GMI said the site is 200 metres from Bristol Temple Meads station and overlooks the city's Floating Harbour.
How the scheme evolved
Chapman Taylor's own releases chart the project from planning to completion. Bristol City Council's planning committee resolved to grant permission in July 2022, when the practice described a 471-bedroom scheme across three buildings around an open courtyard, with a standalone two-storey mixed-use hub on the harbour side.
By the time construction started in August 2024, the practice gave the figure as 447 studio and cluster bedrooms. That number was repeated at topping out and in the completion announcement, and GMI's releases also give 447 beds. None of the sources explains the change.
| Stage (Chapman Taylor release) | Bedrooms |
|---|---|
| Planning resolution, July 2022 | 471 |
| Construction start, August 2024 | 447 |
| Topping out, October 2025 | 447 |
| Completion, November 2026 | 447 |
The description of the buildings also differs between sources. Chapman Taylor's planning and construction-start releases refer to three buildings around an open courtyard plus a standalone hub, and its topping-out release says the 447 bedrooms are spread across three buildings, while its completion release and GMI's releases describe two residential blocks plus the standalone hub.
The naming of the client has shifted too. At construction start, Chapman Taylor named the client as Host Student Housing Ltd, a specialist student accommodation developer and operator, and said it was part of GMI's delivery team. At topping out, GMI said the scheme was being delivered for a joint venture between Host and Corebridge Real Estate Investors. The completion release names Tiger Developments as developer, with funding from Corebridge Financial and Host as operator.
GMI said the final steel beam was raised into place during a traditional topping out ceremony. Jonathan Harris, Director at Chapman Taylor's Bristol studio, said at the time: "Topping out this scheme is a proud moment for everyone involved."
GMI had set out a two-year build programme to complete for the start of the 2026 academic year, and Chapman Taylor had targeted completion in early summer 2026 for the autumn intake.
The campus opposite
Chapman Taylor said Waterside's completion coincides with the opening of the University of Bristol's Temple Quarter Enterprise Campus directly opposite, which it expects to accommodate about 4,500 students and 650 staff.
The university said the 38,000 square metre building opened on 7 September 2026 and provides space for around 4,500 students, 650 staff and industry and community partners.
Jonathan Harris joined Chapman Taylor's Bristol studio in 2016 and became a Director in 2022, according to the practice.
On the record: Chapman Taylor, Bristol City Council
Sources
- Chapman Taylor (opens in a new tab) (accessed 2026-11-21)
- Chapman Taylor (opens in a new tab) (accessed 2026-11-21)
- Chapman Taylor (opens in a new tab) (accessed 2026-11-21)
- Chapman Taylor (opens in a new tab) (accessed 2026-11-21)
- GMI Construction Group (opens in a new tab) (accessed 2026-11-21)
- GMI Construction Group (opens in a new tab) (accessed 2026-11-21)
- Host (opens in a new tab) (accessed 2026-11-21)
- University of Bristol (opens in a new tab) (accessed 2026-11-21)
This story was researched from the primary sources above and checked against them before publication. Spotted an error? Tell us and we will correct it promptly.